Planning approved: what to do next
Approval is the start, not the finish. Most extensions need about seven firms before the last tile goes down, and the order you book them in decides how soon you can start.
Read your decision notice first
Your approval comes with conditions. Some only matter at the end, such as matching brickwork. Others, often called pre-commencement conditions, must be signed off by the council before any work starts. Common ones cover materials, drainage and protecting trees. Send the details the condition asks for early, because sign-off can take up to eight weeks.
Permission usually lasts three years from the date on the notice. Work has to begin within that time or you'll need to apply again.
1. Building regulations drawings
Planning drawings show what the extension looks like. They don't show how it's built. An architect or technician now turns them into building regulations drawings, with the foundations, insulation, drainage and fire safety a builder needs to give you a real price. Start this straight away, as it usually takes four to six weeks.
2. Structural calculations
Taking out a back wall, opening up a kitchen or adding a dormer means steel beams. A structural engineer sizes them and the foundations, and building control will want the calculations before it signs anything off. The engineer usually works from your architect's drawings, so book them together.
3. Party wall notices
If you share a wall with a neighbour, or you're digging foundations close to their house, the Party Wall etc. Act 1996 means you must serve notice before work starts. For work on a shared wall that's two months' notice, so this is the step that most often holds a build up. Our party wall guide explains it in full.
4. Builder quotes
With drawings and calculations in hand, a builder can give you a fixed, written quote instead of an estimate. Ask what's included, what isn't, how payments are staged and how long the build will take. Good builders in North London are often booked two to four months ahead, so get quotes while the paperwork is being finished.
5. Glazing and rooflights
Bifolds, sliding doors and big rooflights are made to measure and often take eight to twelve weeks. Order them early enough that they arrive when the shell is up, or the site sits waiting with a tarpaulin across the back of the house.
6. Skip and site set-up
A skip on the road needs a council permit, which the skip firm normally arranges. If the skip can go on your drive, you don't need one. Book it for the first day on site.
7. Kitchen
Most kitchen extensions end with a new kitchen. It's measured once the walls are up and fitted after plastering, but order it during the build, as many kitchens take six to ten weeks to make.
Before you start: building control and the rest
You need building regulations approval as well as planning permission. You can use the council's building control team or a registered building control approver. They inspect the work as it goes and issue a completion certificate at the end, which you'll need if you ever sell.
If there's a public sewer within three metres of the new foundations, you'll usually need a build-over agreement from the water company. Tell your home insurer before work begins, too.
Common questions
How long does planning permission last?
Usually three years from the date on the decision notice. Work must begin within that time, unless your notice says otherwise.
Can I start work as soon as I'm approved?
Only once any pre-commencement conditions are signed off, building regulations are in place and party wall notices have been settled with your neighbours.
Do I need building regulations if I have planning permission?
Yes. Planning permission covers how the extension looks and its effect on neighbours. Building regulations cover how it's built, and you need both.
Who should I book first after approval?
An architect or technician for building regulations drawings, and a structural engineer. Serve party wall notices at the same time, as they need up to two months.