Party wall notices for extensions and lofts
If you share a wall with a neighbour or you're digging near their house, you'll probably need to serve a party wall notice. Get it out early, because the notice period can be the longest wait before a build starts.
When you need one
The Party Wall etc. Act 1996 covers England and Wales. It applies to three kinds of work that extensions and lofts often involve:
Work on a shared wall, such as cutting in steel beams for a loft or a knock-through, raising the wall, or cutting in flashings. This needs two months' notice.
Building a new wall on or up to the boundary line, which is common with side and rear extensions. This needs one month's notice.
Digging foundations within three metres of a neighbour's building and deeper than its foundations, or within six metres in some cases. This needs one month's notice.
What happens after you serve it
Your neighbour has 14 days to reply. They can agree, or they can dissent and ask for a party wall award. If they don't reply at all within 14 days, the law treats it as a dispute and a surveyor has to be appointed.
Neighbours can share one agreed surveyor or each appoint their own. The surveyor records the condition of the neighbour's property before work starts and writes an award setting out how and when the work can be done.
Who pays
The person doing the work normally pays the surveyors' fees, including the neighbour's surveyor. Using one agreed surveyor for both sides is usually cheaper.
Good to know
Planning permission doesn't remove the need for a party wall notice. A notice lapses if work hasn't started within a year of serving it. And talking to your neighbours before the notice lands makes a quick agreement far more likely.
Common questions
Do I need a party wall agreement for a rear extension?
Often, yes. If the extension sits on or near the boundary, or the foundations are dug close to your neighbour's house, you'll need to serve notice under the Party Wall etc. Act 1996.
Does a loft conversion need a party wall notice?
In a terraced or semi-detached house it usually does, because the steel beams are normally set into the shared wall. That needs two months' notice.
What if my neighbour doesn't respond to a party wall notice?
If there's no reply within 14 days, it's treated as a dispute and a party wall surveyor has to be appointed to agree an award.
Who pays for the party wall surveyor?
The person doing the work normally pays for both surveyors, or for one agreed surveyor acting for both sides.